Section 12-K-A02. A102 - APPLICABILITY AND CONFORMANCE  


Latest version.
  • 5 DCMR § 2100

    APPENDIX APROJECT ELECTIVES

     

    Appendix A to the International Green Construction Code is adopted and incorporated into the Green Construction Code as Appendix A with the following modifications.

     

    A102APPLICABILITY AND CONFORMANCE

     

    Strike Section A102.2 of Appendix A in the International Green Construction Code in its entirety and insert new Section A102.2 in Appendix A of the Green Construction Code in its place to read as follows:

    A102.2 Required number of and selection of project electives.  New construction projects shall attain a total of 15 project electives, and Level 3 alterations shall attain 13 project electives. Selected project electives shall be applied as mandatory requirements for the project.  Selected project electives shall be communicated to the code official in the manner and form specified by the code official.

     

     

authority

Section 10 of the Construction Codes Approval and Amendments Act of 1986 (Act), effective March 21, 1987 (D.C. Law 6-216; D.C. Official Code § 6-1409 (2012 Repl.)) and Mayor’s Order 2009-22, dated February 25, 2009, as amended.

source

Final Rulemaking published at 61 DCR 3356 (March 28, 2014 – Part 2); as corrected by Errata Notice published at 61 DCR 5246 (May 23, 2014).

EditorNote

The District of Columbia Green Construction Code (2013) , referred to as the “Green Construction Code,” consists of the 2012 edition of the International Green Construction Code published by the International Code Council (ICC), as amended by the District of Columbia Green Construction Code Supplement (2013)(12 DCMR K). The International Green Construction Code is copyrighted by the International Code Council and therefore is not republished here. However, a copy of the text may be obtained at:http://publicecodes.cyberregs.com/icod/igcc/2012/index.htm?bu=IC-P-2012-000023&bu2=IC-P-2012-000019.