Chapter 12-K9. COMMISSIONING |
Section 12-K903. COMMISSIONING
-
Strike Chapter 9 of the International Green Construction Code in its entirety and insert new Chapter 9 in the Green Construction Code in its place to read as follows:
903.1 General. Where application is made for construction as described in this section, the registered design professional in responsible charge or approved agency shall perform commissioning during construction as required by Table 903.1 and by Administrative Bulletins. The approved agency shall be qualified and shall demonstrate competence, to the satisfaction of the code official, for the commissioning of the particular type of construction or operation in accordance with the qualification requirements set forth in Administrative Bulletins. The registered design professional in responsible charge and engineers of record involved in the design of the project are permitted to act as the approved agency provided those personnel meet the qualification requirements set forth in the Green Building Program Manual to the satisfaction of the code official.
903.2 Preliminary commissioning report requirement. The approved agency shall keep records of the commissioning required by Table 903.1. The approved agency shall furnish commissioning reports to the owner and the registered design professional in responsible charge and, upon request, to the code official. Reports shall indicate that work was or was not completed in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. Where discrepancies are not corrected, they shall be brought to the attention of the owner, code official and to the registered design professional in responsible charge prior to the completion of that phase of the work. Prior to the final inspection, a Preliminary Commissioning Report shall be provided to the owner and a copy shall be made available to the code official upon request.
903.3 Final commissioning report requirement. A Final Commissioning Report shall be provided to the owner within 180 days after the date of issuance of a the first certificate of occupancy for occupiable space in a story above grade plane, and a copy shall be made available to the code official upon request.
TABLE 903.1
COMMISSIONING PLAN
CONSTRUCTION OR SYSTEM REQUIRING VERIFICATION
PREOCCUPANCY
METHOD
OCCURRENCE
SECTION/
REFERENCED STANDARDPreoccupancy
Chapter 4: Site Development and Land Use
Landscape irrigation systems
X
Field-inspection
Installation
Section 614 of the Plumbing Code
Stormwater management system operation
None
Field-inspection
Installation
21 DCMR (Water and Sanitation),
Chapter 5 (Water Quality and Pollution)Site lighting
X
Testing and report
Installation
409
Chapter 6: Energy
Energy consumption, monitoring, targeting and reporting
a. Monitoring system
X
Inspection and verification
During construction and
prior to occupancy603
b. Calibration
X
Testing and review and evaluation or test reports
During commissioning
603
Mechanical systems completion
a. Air system balancing – provide the means for system balancing
X
Inspection and verification
During construction and
prior to occupancy611.1.2.1 and through reference to Energy Conservation Code
b. Hydronic system balancing – provide means for system balancing
X
Inspection and
verificationDuring construction and
prior to occupancy611.1.2.2 and through reference to Energy Conservation Code
c. Mechanical system manuals – construction documents to require O&M manual
X
Verification of construction documents
Plan review
611.1.5.2
Mechanical systems
a. Commissioning required and noted in plans and specifications
X
Verification of
construction
documentsPlan review
611.1
b. Documentation of required commissioning outcomes
X
Verification with the building owner
Subsequent to completion
of all commissioning activities611.1
c. Preparation and availability of a commissioning plan
X
Verification with the RDP or commissioning agent
Between plan review and commissioning initiation
611.1.1
d. Balance HVAC systems (both air and hydronic)
X
HVAC system installer/contractor or commissioning agent
After installation of HVAC systems and prior to occupancy
611.1.2
e. Functional performance testing of HVAC equipment
X
HVAC system installer/contractor or commissioning agent
After installation of HVAC systems and prior to occupancy
611.1.3
f. Functional performance testing of HVAC controls and control systems
X
HVAC system installer/contractor or commissioning agent
After installation of HVAC systems and prior to occupancy
611.1.3.2
g. Preparation of preliminary commissioning report
None
HVAC system installer/contractor or commissioning agent
None
611.1.4
h. Acceptance of HVAC systems and equipment/system verification report
None
Building owner
None
611.1.4.1
i. Preparation and distribution of final HVAC system completion. Documentation that construction documents require drawings, manuals, balancing reports and commissioning report be provided to the owner and that they have been provided
None
RDP, contractor or commissioning authority
None
611.1.5
Chapter 6: Lighting
Verification of lamp
X
Field inspection
Final inspection
611.3
Verification of ballast
X
Field inspection
Final inspection
611.3
Lighting Controls
a. Installation
X
Field inspection
Final inspection
611.3.2
b. Calibration
X
System installer/Contractor or commissioning agent
Final inspection
611.3
Chapter 7: Water Resource Conservation, Quality and Efficiency
Cooling tower performance
—
—
—
703.7.7
Metering
X
—
—
705.1.1
Chapter 8: Indoor Environmental Quality and Comfort
Air-handling system access
X
Field inspection and verification
During construction and prior to occupancy
802.2
Air-handling system filters
X
Field inspection and verification
During construction and prior to occupancy
802.3
For SI: 1 square foot = 0.0929 m2.