Section 15-2105. ALTERNATIVE OVERHEAD TRANSMISSION LINE ROUTES  


Latest version.
  •  

    2105.1The description of each alternative route considered for the transmission line shall include the following:

     

    (a)An estimate of the capital and annual operating cost of each alternative route; and

     

    (b)A statement of the reason why each alternative route was rejected.

     

source

Final Rulemaking published at 51 DCR 8643 (September 3, 2004).