D.C. Municipal Regulations (Last Updated: September 13, 2017) |
Title 19. AMUSEMENTS, PARKS, AND RECREATION |
Chapter 19-43. DISTRICT OF COLUMBIA PUBLIC LIBRARY: PROCUREMENT |
Section 19-4327. TIME AND MATERIALS CONTRACT
Latest version.
-
4327.1The CCO shall use a time and materials contract only when it is not possible to estimate accurately the extent or duration of the work or the anticipated costs with any degree of confidence.
4327.2A time and materials contract shall include direct labor hours at specified fixed hourly rates that include wages, overhead, general and administrative expenses, profit and materials required at cost.
4327.3The CCO shall ensure supervision of contractor performance when a time and materials contract is used.
source
Final Rulemaking published at 55 DCR 493 (January 18, 2008).