Section 20-3315. RISK REDUCTION USING INTERIM CONTROLS  


Latest version.
  •  

    3315.1Before any individual performs interim controls to eliminate lead-based paint hazards in the District of Columbia such person shall be trained in the lead-safe work practices set forth in § 3302.

     

    3315.2A certificate of completion from an EPA- or DDOE-accredited training provider or from another EPA-authorized, state-accredited training provider shall serve as proof of receipt of the lead-safe work practices training required by these regulations. An individual shall provide proof of training in lead-safe work practices upon request by DDOE at the job site. A business entity shall ensure that its workers comply with these standards.

     

    3315.3Documentation proving Certified Renovator status, or Abatement Worker or Abatement Supervisor certification status, shall satisfy the requirements of §§ 3315.1 and 3315.2, provided such documentation is from an EPA- or DDOE accredited training provider or from another EPA-authorized, state-accredited training provider.

     

    3315.4Whenever non-abatement activities are conducted to address lead-based paint hazards pursuant to an Order to Eliminate Lead-Based Paint Hazards, a clearance examination shall be required:

     

    (a)No sooner than one (1) hour after completion of such interim controls, but  no more than three (3) business days after such completion, and again  between thirty (30) and thirty-six (36) months, as specified by DDOE in  the Order, after completion of the interim controls activities; or

     

    (b)No sooner than one (1) hour after completion of such interim controls, but  no more than three (3) business days after such completion, and again  within such timeframe that is specified by DDOE in the Order, which may  include a requirement for multiple Clearance Reports  over time.

     

    3315.5An initial clearance report pertaining to the elimination of lead-based paint hazards identified in an Order issued by DDOE shall be issued only by a risk assessor. Any subsequent clearance report may be issued by either a risk assessor, a lead-based paint inspector, or a dust sampling technician.

     

    3315.6Each clearance report shall contain a copy of the current DDOE-issued certification card belonging to the individual that conducted the clearance examination and the date the clearance report was issued.

     

    3315.7Notice to DDOE that a dust test will be performed as part of a clearance examination pursuant to § 3315.4 shall be provided by fax, in person, or via the DDOE website, on a DDOE-specified form, submitted to DDOE at least twenty-four (24) hours prior to conducting the dust test, or as soon as practicable, whichever is sooner.

     

    3315.8A copy of each clearance report shall be submitted to DDOE by the property owner, within seven (7) business days of its issuance, either in PDF format by email, or by mail, a courier service, or in person.

     

authority

District Department of the Environment Establishment Act of 2005, effective February 15, 2006 (D.C. Law 16-51; D.C. Official Code § 8-151.01 et seq. (2008 Repl. & 2012 Supp.)), the Childhood Lead Screening Amendment Act of 2006, effective March 14, 2007 (D.C. Law 16-265; D.C. Official Code § 7-871.03 (2008 Repl. & 2012 Supp.)), the Transfer of Lead Poison Prevention Program to the District Department of the Environment Amendment Act of 2008, effective August 16, 2008 (D.C. Law 17-219; 55 DCR 7602 (July 18, 2008)), the Lead-Hazard Prevention and Elimination Act of 2008, effective March 31, 2009 (D.C. Law 17-381; D.C. Official Code § 8-231.01 et seq. (2012 Supp.)), Mayor’s Order 2009-113, dated June 18, 2009, and the Lead Hazard Prevention and Elimination Amendment Act of 2010 (“2011 Amendments”), effective March 31, 2011 (D.C. Law 18-348; 58 DCR 717 (January 28, 2011)).

source

Final Rulemaking published at 60 DCR 10909 (July 26, 2013).