Section 20-5804. TANK TIGHTNESS TESTING UPON UPGRADE


Latest version.
  •  

    5804.1Upon completion of an UST system upgrade and prior to placing the UST system in operation, a tank tightness test shall be performed on an UST system that satisfies the precision testing requirements set forth in § 6007, unless the tank is upgraded by cathodic protection and the owner or operator complies with § 5801.5(c).

     

source

Final Rulemaking published at 40 DCR 7835, 7862 (November 12, 1993); as amended by Final Rulemaking published at 46 DCR 7699 (October 1, 1999).