Section 22-B8003. REVIEW FACTORS  


Latest version.
  •  

    8003.1The Director shall review applications and make awards based upon the following criteria:

     

    (a)Feasibility of the project;

     

    (b)Soundness of research design, statistical technique, and procedures and methodology, if appropriate; and

     

    (c)Theoretical and technical soundness of the proposed plan of operation including consideration of the extent to which:

     

    (1)The objectives of the proposed project are clearly defined and clearly stated;

     

    (2)Proposed project activities appear likely to reach objectives;

     

    (3)The proposed project would contribute to the achievement of the grant’s stated policy objectives; and

     

    (4)Provisions are made for adequate evaluation of the effectiveness of the project and for determining the extent to which the objectives are accomplished.

     

source

Final Rulemaking published at 38 DCR 4431, 4433 (July 19, 1991).