Section 25-C501. EQUIPMENT ROOMS - FLOOR COVERING*  


Latest version.
  •  

    501.1The equipment room floor shall be of concrete or other nonabsorbent material having a smooth slip resistant finish and shall have positive drainage, including a sump pump if necessary.

     

    501.2Ancillary equipment, such as a heater, shall be stored in an equipment room as specified in Subsection 500.1.

     

     

authority

Section 4902 of the Department of Health Functions Clarification Act of 2001 (“Act”) effective October 3, 2001 (D.C. Law 14-28; D.C. Official Code § 7-731(a)(11) (2012 Repl. & 2016 Supp.)), and Mayor’s Order 2001-111, dated August 6, 2001.

source

Final Rulemaking published at 64 DCR 5359 (June 9, 2017).