Section 27-1540. BID EVALUATION  


Latest version.
  •  

    1540.1The contracting officer shall determine whether a prospective contractor is responsible and whether the prices offered are reasonable.

     

    1540.2Prompt payment discounts shall not be considered in the evaluation of bids.  However, any discount offered shall form a part of the award and shall be taken by the District if payment is made within the discount period specified by the bidder.

     

authority

The Chief Procurement Officer of the District of Columbia (CPO), pursuant to the authority set forth in sections 401, 402, 409, 414, 1102, and 1106 of the Procurement Practices Reform Act of 2010, effective April 8, 2011 (D.C. Law 18-371; D.C. Official Code §§ 2-354.01, 2-354.04, 2-354.14, 2-361.02 and 2-361.06 (2011 Repl.)) (Act).