D.C. Municipal Regulations (Last Updated: September 13, 2017) |
Title 27. CONTRACTS AND PROCUREMENT |
Chapter 27-32. CONTRACT FINANCING AND FUNDING |
Section 27-3223. RISK OF LOSS
Latest version.
-
3223.1The contracting officer shall include a provision, approved by the Director, with the progress payment provisions of the contract which provides that, except for normal spoilage, the contractor shall bear the risk of loss, theft, destruction, or damage to property affected by the provision, unless the District has expressly assumed that risk.
3223.2The contractor shall be obligated to repay the District the amount of unliquidated progress payments based on costs allocable to the property if the loss occurred after the contractor assumed the risk of loss.
3223.3The contractor shall not be obligated to pay for the loss of property for which the District has assumed the risk of loss.
source
Final Rulemaking published at 35 DCR 1637 (February 26, 1988).