Section 27-3704. SETTLEMENT MEMORANDUM  


Latest version.
  •  

    3704.1At the conclusion of settlement negotiations, the contracting officer shall prepare a settlement memorandum containing the principal elements of the settlement for inclusion in the contract file.

     

    3704.2If the settlement was negotiated on the basis of individual items, the contracting officer shall specify the factors considered for each item. If the settlement was negotiated on an overall lump-sum basis, the contracting officer shall not have to evaluate each item or group of items individually, but shall support the total amount of the recommended settlement in reasonable detail.

     

    3704.3The settlement memorandum shall include explanations of matters involving differences and doubtful questions settled by agreement and the factors considered.

     

source

Final Rulemaking publishing at 35 DCR 1695 (February 26, 1988).