Section 27-4104. PROVISION OF MATERIAL FOR PERFORMING CONTRACTS  


Latest version.
  •  

    4104.1Except as provided otherwise in this section, each contractor and subcontractor shall furnish all material for performing District contracts.

     

    4104.2The contracting officer may provide material to the contractor or subcontractor when necessary to achieve significant economy, standardization, expedited production, or when it is otherwise determined to be in the best interest of the District.

     

    4104.3The solicitation shall specify material that the District will furnish in sufficient detail to enable offerors to accurately evaluate and respond to the solicitation.

     

     

authority

Sections 204 and 1106 of the Procurement Practices Reform Act of 2010, effective April 8, 2011 (D.C. Law 18-371; D.C. Official Code §§ 2-352.04 and 2-361.06 (2012 Repl.)).

source

Final Rulemaking published at 35 DCR 1733 (February 26, 1988); as amended by Final Rulemaking published at 63 DCR 10016 (July 29, 2016).