Section 30-2227. POSTPONEMENT OF BID OPENING  


Latest version.
  •  

    2227.1The contracting officer may postpone a bid opening until after the time scheduled for bid opening under the following circumstances:

     

    (a) If the contracting officer has reason to believe that the bids of an important segment of bidders have been delayed in the mail for causes beyond the control of bidders without fault or negligence, such as flood, fire, accident, weather conditions, or strikes; or

     

    (b) If unanticipated events interrupt normal governmental processes so that the conduct of bid openings as scheduled is impractical.

     

    2227.2At the time of a decision to postpone a bid opening, an announcement decision shall be publicly posted. If practical, before the issuance of a formal amendment of the IFB, the decision shall be informally communicated to prospective bidders who are likely to attend the scheduled bid opening.

     

    2227.3When a bid opening is postponed, the time of actual bid opening shall be the time established in determining "late bids" or other late actions under § 2222.

     

    2227.4The contracting officer shall prepare a written memorandum for the file explaining the circumstances of the postponement.

     

    2227.5The contracting officer may proceed with the bid opening as soon as practical after the original scheduled time without prior amendment to the IFB or notice to bidders, whenever any delay incident to the issuance of the amendment or notice would not be in the best interests of the Agency.

     

source

Final Rulemaking published at 36 DCR 6681, 6726 (September 22, 1989).