Section 30-2240. BID EVALUATION  


Latest version.
  •  

    2240.1The contracting officer shall determine whether a prospective contractor is responsible and whether the prices offered are reasonable.

     

    2240.2Prompt payment discounts shall not be considered in the evaluation of bids, However, any discount offered will form a part of the award and the discount will be taken by the Agency if payment is made within the discount period specified by the bidder.

     

source

Final Rulemaking published at 36 DCR 6681, 6732 (September 22, 1989).