Section 9-362. DETERMINATION OF ASSESSED VALUE OF REAL PROPERTY WITH CONSTRUCTION IN PROGRESS  


Latest version.
  •  

    362.1For construction in progress, sixty-five percent (65%) complete shall be based on how components of an improvement contribute to the overall base structure. A tenant finish is not a component of a structure that contributes to the overall base structure.

     

    362.2The following guide shall be used to estimate the percentage of completion for a single family detached residence:

     

    PERCENTAGE OF COMPLETION

     

     

    Percentage of total

    Cumulative Percentage of total

    Plans, permits and survey

    2%

    2%

    Excavation, forms, water/sewage hookup

    hookup

    4

    6

    Concrete

    8

    14

    Rough framing

    21

    35

    Windows and exterior doors

    2

    37

    Roof cover

    3

    40

    Rough-in plumbing

    4

    44

    Insulation

    1

    45

    Rough-in electrical and mechanical

    11

    56

    Exterior

    6

    62

    Interior

    8

    70

    Built-in cabinets, interior doors, trim, etc.

    etc.

     

    13

    83

    Plumbing

    5

    88

    Floor covers

    3

    91

    Built-in appliance

    3

    94

    Light fixtures and finish hardware

    2

    96

    Painting and decorating

    4

    100

     

    100%

     

     

    362.3The following guide shall be used to estimate the percentage of completion for all other structures:

    PERCENTAGE OF COMPLETION

     

    Percentage of total

     

    CumulativePercentage

    of total

    Plans, permits, and survey

    2%

    2%

    Foundation

    6

    8

    Slab and Frame

    24

    32

    Exterior Walls

    14

    46

    Roof

    2

    48

    Electricity

    5

    53

    Heat & Air Conditioning

    15

    68

    Plumbing

    9

    77

    Misc. Equip., Elevators, Etc.

    2

    79

    Sprinklers

    2

    81

    Interior Partitions (Studding),

     

     

    Interior Finish (Lath) (Dry Wall)

     

     

    (Plaster) (Tape), Carpentry & Millwork., Tiling, and Flooring

    15

    96

    Paint

    2

    98

    Landscape, Paving

    2

    100

     

    100%

     

     

     

    362.4For renovations, additions that are not new structures, and other additions, the Deputy Chief Financial Officer may consider the taxpayer's submitted "Schedule of Costs" (FP 315) when determining the assessed value of the real property.

     

    362.5In determining the assessed value of real property where there is construction in progress and sixty-five percent (65%) of the total estimated construction is determined to be complete, the Deputy Chief Financial Officer may consider the "Schedule of Costs" (FP 315).

     

    362.6In considering the "Schedule of Costs," the Deputy Chief Financial Officer shall rely primarily on the Percentage of Completion Guides in §§ 362.2 and 362.3.

     

source

Final Rulemaking published at 40 DCR 8171, 8173 (November 19, 1993).