5748043 Resolution 21-271, Change Order Nos. 11 and 12 to Contract No. GF-2010-C-0030 Approval and Payment Authorization Emergency Declaration Resolution of 2015  

  • A RESOLUTION

                                                            

    21-271

     

    IN THE COUNCIL OF THE DISTRICT OF COLUMBIA

     

    November 3, 2015         

     

                                                                                                                                                 

    To declare the existence of an emergency with respect to the need to approve Change Order Nos. 11 and 12 to Contract No. GF-2010-C-0030 with Parkinson/Forrester UDC Student Center JV, LLC for the construction of the New Student Center at the University of the District of Columbia, Van Ness Campus, and to authorize payment in the aggregate amount of $3,584,222 for the goods and services received and to be received under the contract. 

     

    RESOLVED, BY THE COUNCIL OF THE DISTRICT OF COLUMBIA, That this resolution may be cited as the “Change Order Nos. 11 and 12 to Contract No. GF-2010-C-0030 Approval and Payment Authorization Emergency Declaration Resolution of 2015”.

               

    Sec. 2.  (a) There exists an immediate need to approve Change Order Nos. 11 and 12 to Contract No. GF-2010-C-0030 for the construction of the New Student Center at the University of the District of Columbia, Van Ness Campus, and to authorize payment in the aggregate amount of $3,584,222 for the goods and services received and to be received under the contract. 

    (b)  On January 21, 2011, Contract No. GF-2011-C-0030 in the amount of $29,899,000 was awarded to Parkinson/Forrester UDC Student Center JV, LLC for the construction of the New Student Center at the University of the District of Columbia, Van Ness Campus.

    (c)  The aggregate value of the additional scope of work under Change Order Nos. 11 and 12 to the contract exceeds $1 million in a 12-month period.

    (d)  Approval of Change Order Nos. 11 and 12 to Contract No. GF-2010-C-0030 in the aggregate amount of $3,584,222 is necessary to compensate Parkinson/Forester UDC Student Center JV, LLC for work performed and to be performed in timely completing the construction of the New Student Center at the University of the District of Columbia, Van Ness Campus.

     

    Sec. 3.  The Council of the District of Columbia determines that the circumstances enumerated in section 2 constitute emergency circumstances making it necessary that the Change Order Nos. 11 and 12 to Contract No. GF-2010-C-0030 Approval and Payment Authorization Emergency Act of 2015 be adopted after a single reading.

               

    Sec. 4.  This resolution shall take effect immediately.